Construction defects in a new-build home are not all claimed in the same way or within the same time limit. A door that sticks, a leaking terrace or a crack in a floor slab carry different guarantees under Spain’s Building Act (Ley de Ordenación de la Edificación, LOE). Knowing which group your problem falls into, when the time limit starts and how to prove it is what separates a claim that succeeds from one that arrives too late.

The three groups of defects and their guarantee periods
The LOE distinguishes three types of material damage to a building and gives each a guarantee period (article 17):
- Ten years for damage affecting the structure: foundations, columns, beams, floor slabs, load-bearing walls and other elements that compromise the strength and stability of the building.
- Three years for defects in building elements or installations that mean the home fails the habitability requirements: health and watertightness (damp, leaks), noise protection, energy saving and thermal insulation, among others.
- One year for workmanship defects in finishes: paintwork, tiling, joinery, trims. The builder is liable for these.
In practice, the line between one group and another is what is most often disputed. A damp patch may be a badly sealed joint or a waterproofing failure that affects habitability. That is why the technical classification of the defect is the first question an expert must answer.
When do the time limits start?
Guarantee periods run from the acceptance of the works (recepción de la obra), not from the day you sign the deed or receive the keys. Acceptance is the act by which the builder hands over the finished works to the developer, recorded in a certificate signed by both. If there were reservations, the period runs from when they were remedied.
Buyers often do not know that date. It is worth asking the developer for it in writing in your first claim, together with the final documentation of the works.
Guarantee and limitation: two different periods
It is not enough for the defect to appear within the guarantee period. Once the damage becomes apparent, the LOE gives two years to bring a claim (article 18). If that time passes without action, the claim is time-barred even if the defect is structural.
That two-year period can be interrupted by a written claim that leaves a record, such as a burofax. That is why it is so important to claim early and in a verifiable way.
Besides the LOE, the buyer can also claim for breach of contract against the seller, usually the developer. For personal actions with no special time limit, the Civil Code sets five years (article 1964). Both routes are compatible and your lawyer will choose the most suitable one. We check this in every instruction, because the time limits depend on the specific dates.
Who do you claim against?
Several parties take part in a new build: developer, builder, designer, works director and site supervisor. Each is liable for their own part, and the developer is always liable to the buyer together with the others. For structural damage in homes there is also usually a ten-year insurance policy (seguro decenal), which gives extra protection if the developer or builder disappears or runs into financial trouble.
Suing everyone “just in case” is not a good idea: anyone who is cleared may claim their costs. The expert report is precisely what identifies the origin of the defect and, with it, who the claim should be directed at.
How a construction defect is proved
The judge is not a technician. They need a report that explains, with photos, measurements and reasoning, what is wrong, why and how much it costs to fix. A good construction expert report answers five questions:
- What the defect is, described and documented with photos and measurements.
- Which LOE group it falls into (finish, habitability or structure), because the time limit depends on it.
- What caused it: a design, workmanship or materials error, or lack of maintenance.
- Who is liable, based on that cause.
- How much the repair costs, with a detailed valuation.
In the meantime, you can help a lot:
- Take dated photos and videos from day one and keep them.
- Gather the deed, the specification of finishes, the sale contract and any emails with the developer.
- Report the defects in writing and keep the proof.
- Do not carry out major repairs before the defect is documented: if you repair without evidence, it is hard to show later what it was like.
Common defects in new builds in Mallorca
On the islands, humidity, salt air near the coast and heavy autumn rain put roofs, terraces and façades to the test. That is why leaks in terraces and flat roofs, rising damp on ground floors, cracks in façades and failures in pool waterproofing are common. If you live in a building, defects in common areas are claimed by the owners’ association: we explain this in roof and terrace leaks in the community: who pays? and on our page for homeowners’ associations.
If the home is not new but resale, the rules change: we cover this in villa in Mallorca with hidden defects: what you can claim.
Frequently asked questions
Does the one-year period for finishes start when I got the keys? No. It runs from the acceptance of the works between builder and developer, which may be earlier than your deed. That is why there is sometimes less time left than it seems.
The one-year guarantee has passed. Can I no longer claim for finishes? A breach of contract claim against the seller may still be available, with a longer time limit. It depends on the dates and the contract, and your lawyer reviews it with the report.
Is damp a finish defect or a habitability defect? It depends on its origin. If it comes from a waterproofing or watertightness failure, it usually affects habitability and has a three-year guarantee. The expert report determines this.
Do I need the expert report before making a claim? It is not compulsory for the first written claim, but it is highly advisable before negotiating seriously or going to court. With the report you know what to ask for and from whom.
Is the report useful if we reach an agreement in the end? Yes. Many claims are settled when the developer or its insurer sees a solid report. If there is no agreement, the same report is filed in court and defended at the ratification hearing.
How we work
Send us the deed, the handover date and photos of the defects by email or WhatsApp. We study them and send you a fixed, no-obligation quote, with a reply the same day. We visit the property in Mallorca, Menorca, Ibiza or Formentera. If there is a lawsuit, we defend the report before the judge at the ratification hearing.